Bowman prepared plans to re-route an existing acid pipeline that encounters a proposed fine ore stockpile. The design work included close coordination with engineering firm that was designing the stockpile. Deliverables included the following:
- Review of the pump system to check the impact of the relocated segment of the pipeline and provide a memorandum of findings
- Plans and profile sheet and details for the re-routed pipe alignment
- Procedures for removal of pre-existing acid pipeline
- Scope of work document, prepare a bid schedule with material takeoff quantities included, and put together a bid package to support bidding.