Confidential Haul Road Culverts

Southeast, AZ

As a result of a new pit being developed at the mine, a haul road was developed from the pit to the existing crushing facility. Bowman designed six (6) culverts that allow stormwater to flow under the new haul road, and provided Construction Quality Assurance and construction management oversight on the culvert construction.