Bowman provided Arc Flash analysis for the 260,000 sq. ft. office building in Falls Church, VA. The short circuit analysis, protection device coordination study, and arc flash analysis provides appropriate equipment ratings and settings for all adjustable overcurrent protective devices that are installed in the building. Arc Flash Study was conducted to calculate the potential arc flash energy at electrical equipment in the system. When the power study was complete, labels were installed on each piece of equipment. The labels identify incident energy available, Arc Flash Hazard boundary, Arc Flash Hazard category and protective equipment required, when working on equipment that is energized.